description != null):?> keywords != null):?> Adhesive Company | Highland Group Live (new)

Adhesive Company

NEEDS-BASED RESULTS

 

Adhesive Company

SITUATION

Supplier of structural adhesives and surface treatments needed help implementing a plan to improve operational performance and position the plant for future growth.

DRIVER GOAL

  • Improve schedule attainment, on-time customer shipments, and productivity.
  • Reduce key customer lead times.
  • Build a platform for improved growth.

RESULT

  • Improved on-time customer shipments by 30%.
  • Improved productivity by 35% and machine utilization by 69%.
  • Reduced key customer lead time from 16 weeks to 6 weeks.
case study image, CS-158 large

Case Study

Improve Operational Performance & Position for Growth

Issue

A supplier of structural adhesives and surface treatments to the aerospace industry enlisted The Highland Group to implement a plan to improve operational performance and position the plant for future growth.

Highland Approach

The team worked with client leadership to define key performance metrics then conducted a baseline study of the operation to understand gaps and constraints. A targeted improvement plan included a focus on capacity planning and scheduling, machine utilization and quality control to decrease lead time and increase on-time shipments. A structured management system built around the defined performance indicators would serve to track productivity gains and build upon improvements for future growth.

Actions Taken

  • Defined, developed and implemented measurable key performance indicators.
  • Developed and implemented a System For Managing to those metrics.
  • Developed and implemented capacity planning and scheduling.
  • Identified constraints and reengineered critical processes.

Improved schedule attainment by

88%

while reducing quality control cycle times from 18 to 6 days